Sl No. |
Procedure
|
Time Taken (days) |
1. |
Preliminary Survey |
7 |
2. |
Notice issued to concerned land owners |
15 |
3. |
Receipt of Form A Rule 3 from Acquiring Agency |
7 |
4. |
Submission of draft of Notification u/s 4(1) of Land Acquisition Act-I,1894 to the Head Office and publication of the Notification in the Government Gazette by the Secretary LR&DMD |
30 |
5. |
Public Notice issued u/s 5’A’ |
30 |
6.** |
Submission of draft of Declaration u/s 6 of Land Acquisition Act-I,1894 and publication in the Government Gazette by the Secretary,LR&DMD |
45 |
7. |
Request of Order of Acquisiton and approval of the Government for the acquisition |
20 |
8. |
Survey and demarcation of the proposed land for acquisition |
6 |
9. |
General Notice Clause (I)&(II) and (III)& (IV) u/s 9 of the Land Acquisition Act-I,1894 |
30 |
10. |
Hearing of Claims and Objections from parties upon the proposed land to be acquired |
15 |
11. |
Submission of draft of Award Declaration u/s 11 of the Land Acquisition Act-I,1894 and approval of the Government |
60 |
12. |
Disbursement of Compensation |
- |
13. |
Handing and taking over of land between the acquiring agency and the landowners |
7 |
14. |
Mutation of acquired land and issue of Parcha |
2 |
Total time taken: 274 |